A 2,032 kL Detention Vault, Cleaned Out in Five Days
The asset
An underground on-site detention vault in Sydney: 2,032 kL of storage, 54.5 m long, with a filter bay of cartridge filters at the outlet end. The only way in is through the access lids, so every hour inside is confined-space work.
The challenge
A rain event washed silt through the system and across the vault floor ahead of handover. The silt was fine and runny and flowed back as soon as it was disturbed, and the floor is very flat, so it would not run to a pick-up on its own.
What we did
Every entry ran under a confined space permit with continuous gas monitoring, a standby person and rescue equipment at the access point. From day three we worked the vault in zones: sandbag bunds formed working boxes with fixed vacuum pick-ups, flushed from the high end toward the filter bay so recovered silt could not run back over finished areas. The filter bay was cleaned last. Large-capacity equipment, including our 13,500L Combination Unit, was scaled to the volume.
The result
204.92 tonnes of silt and sediment-laden water removed in 23 loads over five days, all transported under our EPA licence with tipping dockets. The vault was inspected and accepted on site by the client's representative, and our condition report flagged the defects we found for the owner to fix.
Got a Large OSD or GPT That's Overdue?
Tell us the asset, when it was last cleaned and the access situation. We'll quote it straight.
Get a Quote or Book a Job
Our 4-step form captures everything we need. Pick "Quote" if you're shopping for pricing, or "Book" if you're ready to schedule.